After the previous re-evaluation of my briefs, I updated the brief sheets for all of the briefs for this year.  At this point I have also removed the three briefs I was unsure about.

Briefs




Brief Summary


The brief summary is useful to me as it shows the current progress of the briefs in one document instead of having to look over all the individual brief sheets.

Currently I have 3 briefs on going, however Brief 5: The Woodshop has not had any further progress since last speaking to the client at the beginning of November. They have assured me that they do want me to do this brief, however at this point it seems highly unlikely. Brief 1 & 11 are side by side projects and I aim to complete them both at the same time, however do not want to rush either of them.

Brief 7: YCN Syfy will be started on w/c 2nd Feb. The deadline for YCN is March 19th. I am aiming to have this completed for that date, using 6 weeks to fulfil the brief.

Brief 12: Ampersandwich is a new addition to my briefs. This was a brief created last year for the OUGD504 module (Link). I enjoyed the brief and the concept, however my execution of the brief was not the best, and I would really like to to be able to include it in my portfolio, so have decided to rebrand it and update it all. I have decided this will only be a small project, with 1 - 2 weeks work as the majority of the work is already completed. It's just a case of rebranding, which I already have a few ideas for.